I finally finished the plumbing over the weekend and yesterday we had the plumbing/framing inspection. I had to add some cleanout ports for the branch drains, since they are over 5 feet long (nothing I read gave me any such clues). So, we're ready for the re-inspection. Meanwhile, Dale and Les are working on insulating the exterior walls. The sheet rock will go up next week provided that we pass the plumbing/framing re-inspection and the insulation inspection.